# Site visit north lot Site visit notes, September 20th. We walked the north lot with the contractor. The drainage on the east side still pools after rain, so the grade needs to be recut before the slab is poured. Action item, get a revised quote from the excavation crew by Friday. Second item, the electrical panel location moves to the west wall, which shortens the conduit run. I took a photo of the pooling area and one of the panel wall. Decision, we approved the western panel location. Open question, does the city inspector need to sign off on the regrade before we pour?