Site visit north lot
Walked the north lot with the contractor. The east side still pools after rain, so the grade has to be recut before the slab is poured, and a revised excavation quote is due Friday. The electrical panel moves to the west wall, shortening the conduit run; that location was approved on site. One question is still open: whether the city inspector must sign off on the regrade before the pour.
Key points
- Drainage on the east side still pools after rain.
- Grade needs to be recut before the slab is poured.

- Electrical panel location moves to the west wall, which shortens the conduit run.
- Western panel location was approved.

- Open question: does the city inspector need to sign off on the regrade before the pour?
Action items
- Get a revised quote from the excavation crew by Friday.
- Confirm whether the city inspector must sign off on the regrade before the pour.